Reply To: Project schedule in the old html format MSOP 2003

Home Forums Discussion Project schedule in the old html format MSOP 2003 Reply To: Project schedule in the old html format MSOP 2003

#6976
Avatar photoCommunity
Keymaster

File | Save As Excel Workbook.   Select the fields you require (defined as a map) , and it’ll save as an xls file.  If you require to do this multiple times, save the map” too.  In order to keep the hiearchy, you’ll need to include the Outline Level, but this won’t auto indent it in Excel, you’ll need to write a macro to do that.