Reply To: Project Server 2007 Resource % allocated to a Task Changing

Home Forums Discussion Forum Project Server 2007 Resource % allocated to a Task Changing Reply To: Project Server 2007 Resource % allocated to a Task Changing

#6441
so then project uses this new % to allocate the remaining time across the rest of the duration of the project? is this correct?