Reply To: Project Server 2007 Resource % allocated to a Task Changing

Home Forums Discussion Forum Project Server 2007 Resource % allocated to a Task Changing Reply To: Project Server 2007 Resource % allocated to a Task Changing

#6442
Preeti Dimble
Keymaster
Richard,
Great question, and the short answer is no.  For examples:  In 2007, work allocation would continue based on the allocation at the assignment finish date when extending the task duration.  In 2010, work allocation would continue based on the Assignment Units.  Entering time would simply move the finish date in or out without affecting work allocation.  Additional information can also be found in the following technet article: https://blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx
Hope this all helps.  Great topic…
Larry Christofaro