Reply To: Project Server 2007 Resource % allocated to a Task Changing

Home Forums Discussion Forum Project Server 2007 Resource % allocated to a Task Changing Reply To: Project Server 2007 Resource % allocated to a Task Changing

#6443
But that is not what i am seeing happen in 2007.  when actual hours are entered on the MY TASKS screen, Accepted, and then the project is published the units is changing.  Then Project is using this new percentage in the units field to distribute the remaining hours into the future instead of using the original percentage I input on the task form for that resource.  i have reports showing future remaining work and after the percent has changed you can see the new percentage is used to calculate the remining hours per week.
is there a patch or hot fix that i need to apply?  i am on Microsoft Office Project 2007 (12.0.6211.1000) SP 1 MSO (12.0.6554.5001)