Reply To: Project Server 2007 Resource % allocated to a Task Changing

Home Forums Microsoft Project Discussion Forum Project Server 2007 Resource % allocated to a Task Changing Reply To: Project Server 2007 Resource % allocated to a Task Changing

#6447
Avatar photoCommunity
Keymaster
Richard,
There have been several updates to Project Server 2007 since your latest.  I suggest updating to the most current SP and CU and then see if the problem persists.
Thanks,
Larry Christofaro