Home › Forums › Discussion › Project Server 2007/2010 CALS and project workspace access › Reply To: Project Server 2007/2010 CALS and project workspace access
I believe the answer is a bit more complicated than a yes or no. It is my understanding that if the site includes a list or view of Project Server data than you need a CAL. If it is just the project site with information (like risks, issues, and other lists), than the user does not need a CAL. In other words, they would need a CAL if you included Project Server web parts or other custom web parts pulling data from Project Server. The BI site would require a CAL. I would be interested in hearing if someone has another view or if things have changed. Hope that helps…