Laurel,

I’ve worked with many lookup tables in 2010 and haven’t seen that issue before.  I also setup a quick test with expected results that behave as they did in 2007.  Have you tried to recreate this in another lookup table?  Did you try deleting the entry, saving the table, and then recreating the entry again?  I’m just wondering if it is a one time corrupted piece of data or a wider spread issue in your environment.  Hope that helps…