Loading...
Quick Links

Reply To: Project Server reporting and Vendor plans

Home Forums Discussion Project Server reporting and Vendor plans Reply To: Project Server reporting and Vendor plans

#6159
CommunityCommunity
Keymaster
Hi Jennifer,
It depends what your tring to do. Most places Ive worked treat the vendor activities as part of the main project, so;
If you’re looking at a vendor Subproject in Project server and the vendor cant have access yet you want to feed them dates for activities (as they change) than a SRSS PDF report mailed to them could do the trick.
If you have vendor tasks that you need to report on internally in terms of contract management, then I would create a custom field on the resources with a vendor name and creeate a SRSS report showing estimates v actuals late start, late finish ect…

Simon Newton