Reply To: Project shutting down when linking to a resource pool

Home Forums Microsoft Project Discussion Forum Project shutting down when linking to a resource pool Reply To: Project shutting down when linking to a resource pool

#6415
Avatar photoCommunity
Keymaster
First off, make sure you have installed SP1 and the June Cumulative Update (both free downloads from MSDN).
Templates shouldn’t be attached to pools as their resources get added to teh pool workload. After saving a copy of teh template PMs should only then connect to teh pool, but preferably only after they have edited the schedule so resource usage matches what your resource managers/management/team leaders tell them what resource availability they can have. This avoids garbage data in!