Reply To: PWA field % Complete – how does it compute?

Home Forums Discussion Forum PWA field % Complete – how does it compute? Reply To: PWA field % Complete – how does it compute?

#6865
Velu Rajanbabu
Keymaster

Jane,Great question. % Complete is a product of duration, and % Work Complete is a product of effort. That’s the short version. Try looking at % Work Complete and you should see what you are looking for. Hope that helps…