Jeremy,
I tried to see if a hamock task would work but it didn’t.  There isn’t a way to extend a recurring task as you are asking below.  You can extend a detail task to the end of the project or change the end date of a recurring task which will automatically add recurring entries.
Hope that helps,
Larry Christofaro