There are some other filters that may be of interest… Unstarted Tasks, and UnFinshed Tasks.  Remember there basic rules.
1. There shall be no tasks with a start date left of the status date that are 0% Complete or lack an Actual Start
2. There shall be no tasks with a finish date to the left of the status date that are not 100% complete with an Actual Finish Date.
3. There shall be no task with a start date to the right of the status date with a %complete different from 0.
4. There shall be no finished task with a finish date to the right of the status date.
There are filters (or at least you can create your own) that will do all of this.