Reply To: Resource Pool and/or Master Schedule for Programme using multiple eRooms to store individual Project Schedules?

Home Forums Discussion Resource Pool and/or Master Schedule for Programme using multiple eRooms to store individual Project Schedules? Reply To: Resource Pool and/or Master Schedule for Programme using multiple eRooms to store individual Project Schedules?

#6654
Community
Keymaster

You are working with 2 conflicting requirements.  Using erooms and share resource pools – don’t work.  The links between the MS Project files are exact disk locations.  You are right – erooms is using virtual and web locations which doesn’t work for resource pools.

You might have to let management know that you have a software restriction that will not allow you to do both – they have to pick one or the other.

Have a nice holiday – I am about to leave on 2 months on the road for work – I think you will have more fun. Best of luck to you.

Ellen Lehnert, MS Project MVP