I am having difficulty getting resource leveling to work.

I have 16 subprojectss and 8 resouces. All the subprojects are to be completed within fiscal 2013. All resources are unique and not interchangeable.

Each subproject has one of the resources assigned as the lead and multiple other resources assigned for review or other specific functions.

6 resources work 40 hours per week – (1920 hours per year prior to vacations, holidays and persnal leave), 1 resource works 30 hours per week, one resource works 12 hours per week.