I’ve assigned (non-human) shared work resources at the summary level to communicate when these resources were required, as opposed to tracking hours against them.
I then filtered for the specific resource, printed the Gantt chart and provided that to the “owner” of those resources so I could get what I needed when. (or as close to that as possible)