Hi mpguy,

Welcome to this Microsoft Project forum:)

I don’t think this will be possible.  I think the only way forward is to isolate the particular tasks and create a new project with them  Anyone that has access to a project will see it all.

FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm

Hope this helps – please let us know how you get on 🙂

Mike Glen
MS Project MVP (97-11)