Reply To: Scheduling utilizing calendar days not work days?

Home Forums Discussion Forum Scheduling utilizing calendar days not work days? Reply To: Scheduling utilizing calendar days not work days?

#6893
Preeti Dimble
Keymaster

Jim, what you are doing should work if the project calendar is setup correctly.  You do have one other place to make sure that your calendar is working as expected that may affect some of the things you are doing, but your specific example should work.  To finish setting up calendar options, go to the Options/Schedule tab (2010) or Options/Calendar tab (2007) and make sure that the Hours per day, Hours per week, and Days per month are setup to coincide with your calendar.  But, that shouldn’t” affect your example.  If that doesn’t work and you don’t get other suggestions than feel free to send me your schedule and I can take a look (lchristofaro@epmsolutionpartners.com).  Hope that helps…