Reply To: Should it be possible to run a Visual report from a common resource pool?

Home Forums Discussion Forum Should it be possible to run a Visual report from a common resource pool? Reply To: Should it be possible to run a Visual report from a common resource pool?

#9760

Thank you for the speedy responce Matt.

As you have suggested

  • I have tried to produce a Visual Report  from the common resource pool whilst having only one small project shared with it and I unfortunately get the same response as previously reported.
  • I have checked the service pack status and already have XP SP3 and Project 2010 SP1 so cant see theres a gap there.
  • I have requested our IT department update my laptops MSExcel from 2007 to 2010 tomorrow.

At least I now know that it can be done which is encouraging.

Many thanks for the support & I’ll report back once tested with Excel 2010.