Reply To: Show a task on hold: use Stop and Resume columns?

Home Forums Discussion Forum Show a task on hold: use Stop and Resume columns? Reply To: Show a task on hold: use Stop and Resume columns?

#10598

If a task is marked as partly completed, then in the Gantt chart click and drag the remaining duration. This lets you move the incomplete part to whenever you want it and all actual duration is left in place. I call this “Rip And Drag” or RAD!

I think this also automatically sets a resume date.