Hi Terry

I tried the following with success:

1.       Create and insert your Text1 Field into the Gantt Entry View

2.       Identify your high level tasks by entering   Y   next to them in the Text1 Field

3.       Go To the Calendar View

4.       Select the View Tab

5.       In the Data Group / select the Filter Menu / select New Filter

6.       Name your New Filter

7.        In the And/Or column select AND

8.       In the Filter Name column select Text1

9.       In the Test column select contains

10.   In the Value column type  Y

11.   Apply or Save