Reply To: Some suggestions for next version of MS project

Home Forums Microsoft Project Discussion Forum Some suggestions for next version of MS project Reply To: Some suggestions for next version of MS project

#31086
Todd Peterson
Guest

I would like to see a configuration setting that prevents PMs from adding resources or networking to Summary Tasks.  There are better ways (start/finish milestones, Responsibility columns, etc.) to convey the same intent without causing various crazy issues within a schedule.