Hi Larry

Thank you for your help. I was aware of that possibility, and I have used it before. I was hoping however for something simpler, because if the Status Date is not on a Friday this can be quite cumbersome (I have one project who updates on Tuesday, another one on Thursday), because you have to divide actual work into 2 values. But now I know that this is the only solution.

Again, thanks a lot, Larry!