Hi – is the progress bar not reaching the time-now status line or is it sliding past it? When this has happened to me before, it was due to a day excluded Friday from the calendar like a holiday and looks like the task progress stopped on Thursday. Or I’ve had the progress bar slip into the next Monday. Make sure you’re working time in the calendar ends at 5:00pm. I have had that issue with tasks using odd calendars like second shift or 24hr calendars. Hope you can resolve it.