Home › Forums › Discussion › Status Date = buggy? › Reply To: Status Date = buggy?
This is an issue/problem/bug. I have not fully investigated the behaviour, which is not present in 2007, but to be 100% confindent you need to put “3/5/12 5pm” as the status date (including the time). Sometimes it seems to do OK without the time, but as I said, I haven’t fully investigated.