I don’t have Project Server or Sharepoint; I’ve set up master files and sub files as described.

Yet I need help to to link task dependencies (predecessors) across sub-projects.

When I open the Task Information tab and key “ProjectNameTask#” in the ID column, it correctly notes “External Task” in the Type column.  But when I click OK to close the window, the dependency does not appear…

Am I doing something wrong?