I don’t have Project Server or Sharepoint; I’ve set up master files and sub files as described.
Yet I need help to to link task dependencies (predecessors) across sub-projects.
When I open the Task Information tab and key “ProjectNameTask#” in the ID column, it correctly notes “External Task” in the Type column. But when I click OK to close the window, the dependency does not appear…
Am I doing something wrong?