Reply To: Subplanning within masterplan gives wrong end-date

Home Forums Discussion Subplanning within masterplan gives wrong end-date Reply To: Subplanning within masterplan gives wrong end-date

#6024
Avatar photoCommunity
Keymaster

Depending on how you set up the Master Shell, you may have inadvertently used a "new" file with a start date in the future, compared to the subprojects; You then may have linked a task wing the Master Shell which caused the end-date to shift to the right.

Hope this helps…

Angelo Arcoleo, PMP