Reply To: Task Splits on Tasks with No Resources

Home Forums Reply To: Task Splits on Tasks with No Resources

#6224
Community
Keymaster
I’m working with a supplier schedule that is in MSP 2003, all tasks have a task type of Fixed Duration and logically linked. We are seeing tasks with a split starting part way through the duration of the task and the split (dotted line) visable in the Gantt view until the complete date. Some tasks show the split and some don’t. I don’t understand what criteria is being applied to show some as split. The tasks that do have the split may be in-progress or complete. Anyone have any ideas what is causing this?
Thanks