Hey, Ellen – how are you doing. It’s been a long time.
Anything you want to remove from the Timeline just right click on the task on select Add to timeline and it will remove it. You can also double click on the task and there is an option at the bottom of the General page to display on the timeline.
When you use Timeline view go for higher level tasks (Summaries) and Milestones. Too much detail can’t be seen. Look at my Nov 2011 article for more info. http://www.lehnertcs.com/pdfs/201111_ezine.pdf
Let me know if you need more help.
Ellen Lehnert, MVP, PMP
“