Reply To: Unit value not calculate automatically for fix duration task type when work value change

Home Forums Microsoft Project Discussion Forum Unit value not calculate automatically for fix duration task type when work value change Reply To: Unit value not calculate automatically for fix duration task type when work value change

#6017
Avatar photoCommunity
Keymaster
Project 2010 changes the way this works. Its noe Peak Units that changes. See blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx
Kevin Watson Microsoft