Reply To: Use baselines for schedules at different levels of detail

Home Forums Discussion Forum Use baselines for schedules at different levels of detail Reply To: Use baselines for schedules at different levels of detail

#6571

The official answer is whether these first phases have some stage gate or process signoff, but for the time to snap a baseline it is better to do than to wish you didn’t.  I agree to make sure that you determine a standard baseline strategy (baseline1 always means this and baseline2 always means that).  You are definitely on the right track…  Larry Christofaro