Oliver,
Thank you for your reply.  I’ll give this a try.
The Std. Rate field is time-phased and defaults to hourly.  Does you know of a way to force the Std. Rate field to default to daily?  In our industry, we incur most costs and charge out on a daily basis for same.
Also, do you know of a way to force the entire daily cost to be applied in the case of partial days on the schedule?  I’ve tried using Accrue at Start, but this doesn’t give the desired result.
Thanks again for your time,
Gary