Reply To: Warning message when indenting tasks?

Home Forums Discussion Warning message when indenting tasks? Reply To: Warning message when indenting tasks?

#6331
Avatar photoCommunity
Keymaster
Hello Martin Haerri –
It is stated in Project API documentation (refer
http://msdn.microsoft.com/en-us/library/aa204904(office.11).aspx) that ProjectBeforeTaskChange event doesn’t occur … when changes are made to outline level or outline number … — this means when you outline the tasks this event doesn’t get fired.
I am worried you can’t do this through macros. Instead, take a copy of the "work" to "custom number1 column" and compare the differences using a flag.
Hope this helps
— Sai, PMP, PMI-SP, MCTS Project