Reply To: What is an effective way to report progress for more than 3000 lines project plan?

Home Forums Discussion What is an effective way to report progress for more than 3000 lines project plan? Reply To: What is an effective way to report progress for more than 3000 lines project plan?

#6586
CommunityCommunity
Keymaster

I’ve just completed a project where I used some VBA to create weekly timesheets in Excel for each Resource. I then had more VBA code to update Proejct from the completed timesheets. If VBA isn’t your thing then try saving your schedule to Excel with a filter for all incomplete tasks for next two weeks to Excel with Name, Actual Start, Actual Duration and Remaining duration columns.

Get whoever to fill in progress then open and merge the data into your schedule.