Home › Forums › Microsoft Project Discussion Forum › What is an effective way to report progress for more than 3000 lines project plan? › Reply To: What is an effective way to report progress for more than 3000 lines project plan?
If you are doing this, I would only include Actual Start, Actual Duration, Remaining Duration columns for update. Be sure not to change the schedule before copying updated data back otherwise the paste will have some dire consequences!