Ability to Reference Task B's Field Contents in Task A

Home Forums Discussion Forum Ability to Reference Task B's Field Contents in Task A

Viewing 0 reply threads
  • Author
    Posts
    • #315377
      Scott Brunton
      Participant

      Greetings!

      I would like to be able to reflect the %Complete of one task in a, say, Number field in another task. Can this be accomplished with a Formula that uses the UID of the task being referenced?

      Here is the ‘why’ … I have built a Summary section at the top of the schedule to reflect progress made in a section within the body of the schedule. In particular, I would like to pull the %Complete from the Summary task of that section and drop it into a milestone task at the top. Can be very useful when building Custom Reports.

      Thanks!

Viewing 0 reply threads
  • You must be logged in to reply to this topic.