Adding Details pane in custom view

Home Forums Discussion Adding Details pane in custom view

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #375341
    ChrisK
    Guest

    Does Project give you the option to add the details pane into your custom view? I want to open up a view, have a standard Gantt table in the top view, and a status sheet table in the bottom Details pane, but have not found any options that make me think this is possible without a macro.

    #375356
    Avatar photoLarry Christofaro
    Participant

    Not sure what you mean by a status sheet but you can certainly setup a combination view. Go to any view list and then to More views, and select to create a New view. There you can define it as a single view or a combination view. A combination view is the top/bottom view and can interact depending on what you choose to select. Remember that the bottom view interacts with the top, for instance a Gantt chart on the top will display information on the selected task in the Task form on the bottom. Hope that helps…

Viewing 2 posts - 1 through 2 (of 2 total)