I assigned two resources at differing % to one task of 142 hours. Will be working to break it down under 80 later.
The problem I have is at the end of the task, one of the resources shows no allocation for a period of 5 weeks.
Why won’t MS Project 2010 evenly allocate the resources to the task evenly?
Matt – Since you have hinted one of the resource has no allocation for a period of 5 weeks, check if there are exceptions (holidays) set for this resource. What is the Task type and Effort driven? It would be good if you can provide a screenshot of this assignment?