      P2010 has the Task Inspector to see which task drives its date.  Is there an equivalent in 2007?
      Thanks so much!
      Laura
    • #9969
      Avatar photoCommunity
      Keymaster

      Good Evening Laura,

      The 2007 equivalent to the Task Inspector (in Project 2010) is the functionality of Task Drivers
      In Project 2007, select a task. On the Project menu, click Task Drivers.

      Note you can also keep the Task Drivers open and click from Task to Task.
      Enjoy and let me know if you have any additional questions.

      -Jacques