I’m having troubles with entering actual time on some project tasks. The administration time is fine and some project tasks are fine. There is assignments created for the resource in that time period. Any suggestions on where to look?
Check to see if the tasks are manually scheduled. If they are manually scheduled, you cannot enter actual time on the task. Only auto-scheduled tasks accept actual time.