Applying the Gantt Chart formatting to the Tracking Gantt (MSP2013 Desktop)

Home Forums Discussion Forum Applying the Gantt Chart formatting to the Tracking Gantt (MSP2013 Desktop)

Viewing 1 reply thread
  • Author
    Posts
    • #484027
      Robert Thomas
      Keymaster

      I have been using the Built-In ‘Gantt Chart’ to construct a schedule and I have made many changes to the format of the ‘Gantt Chart’ during this process.  (Color coding on task bars, adding task bar text, fonts and bolding in text, etc.)  I have now set a Baseline for the schedule.  When viewing the ‘Tracking Gantt’ (it is set to the default settings) it appears in no way similar to the ‘Gantt Chart’.

      Is there a technique to apply the Gantt Chart formatting to the Tracking Gantt?

      KMD

    • #485790
      miles goodchld
      Guest

      The easiest way would be to make a copy of the Gantt view and rename it as “my tracking Gantt”. Then swap the table for the same one as is used in the “official” tracking gantt. You will need to add in the tracking Gantt specific bar formats but it sounds like this will be easier than re-creating all your new formats from the Gantt chart?

Viewing 1 reply thread
  • You must be logged in to reply to this topic.