Baseline date on print layout

Home Forums Microsoft Project Discussion Forum Baseline date on print layout

Viewing 1 reply thread
  • Author
    Posts
    • #418686
      Michele
      Guest

      Hello,
      I would like to add the baseline date (date of when I created the baseline) on the layout, like an evidence of which date is took the project status. It is possible? Let me know

    • #418687
      Larry Christofaro
      Participant

      Unfortunately not. It’s been a request for decades. One option is to put it in the notes field for the project summary task (Task 0).