I’m seeking confirmation that there is a known bug in MSP 2007 BCWP calculation. I have the Calculation Option for Earned Value set to [Physical % Complete]. BCWP appears to be calculating correctly (=[Physcial % Complete]*[Baseline Cost]) at the resource level, yet the BCWP at the task level is incorrect and not equal to the roll-up (sum) of resources. This is only true for in-process tasks, but not for every in-process task.
I’m seeking confirmation that there is a known bug in MSP 2007 BCWP calculation. I have the Calculation Option for Earned Value set to [Physical % Complete]. BCWP appears to be calculating correctly (=[Physcial % Complete]*[Baseline Cost]) at the resource level, yet the BCWP at the task level is incorrect and not equal to the roll-up (sum) of resources. This is only true for in-process tasks, but not for every in-process task.