Change Resource calendar

Home Forums Discussion Forum Change Resource calendar

Viewing 1 reply thread
  • Author
    Posts
    • #4850

      I have a distributed team working in two different time zones – India and Netherlands. There is a situation where a resource moves from India to Netherlands. His billing tariff, Calendar(Holidays are different) should change when he starts working from another timezone. I am able to change the tariff with an effective date. But is there a way to change the calendar for this resource with an effective date?

       

      -Jame Paul Thomas Gnanasekaran

       

       

    • #6072

      You can always add the resource as a new resource. That way all historical information about the resource’s efforts in India can be maintained & his/her new resource information can also be maintained. If this is undesirable, you can create new base calendars for both India & the Netherlands, & on the resource form, change the Base calendar to the appropriate one in the Change Working Time dialog. I don’t know of a way to this date based, since it seems to be a manual operation.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.