I have about 100 resources who need to be assigned the India holidays instead of the US ones. I created the new calendar. I expected to be able to select the resources in the Resource Center and then click BULK EDIT to change the calendar for all of them in one action. However, calendar is not a field which can be changed in BULK EDIT.