Changing duration in 2010

Home Forums Microsoft Project Discussion Forum Changing duration in 2010

Viewing 3 reply threads
  • Author
    Posts
    • #5009
      Community
      Keymaster
      Without the built-in macros like 2007 had, what’s the easiest way to change an existing schedule’s duration type?  I’ve changed the settings under File > Options > Schedule but it didn’t change any of the task durations.
      Thanks,
      Ed
    • #6488
      Community
      Keymaster
      I normally insert the column "Type". This gives me the duration type for each activity and the ability to change to another type. Note, it doesn’t include the Effort Driven option.
    • #6493
      Community
      Keymaster
      The settings under File > Options > Schedule will only be taken into account for the newly created tasks. You’ll have the change the duration type for the already existing tasks ‘manually’ (like suggested using the Type column).
    • #6507
      Community
      Keymaster
      Ed,
      Try File/Options/Add-ins and look for the Format Durations add-in.
      Mike Glen
      Project MVP (97-11)
      See https://tinyurl.com/2xbhc for my free Project Tutorials