If the start date of an automatically scheduled task falls on a non-working day, prior to assigning a resource, is there a way to show that, with conditional formatting, or on a custom field?
Ekin;
Can you provide an example.
Generally speaking, Project will only schedule tasks on a working day as defined either by the Project Calendar or the Resource Calendar. If your project calendar says working days are M-F 8-5, and there’s no resource assigned, then project will schedule the tasks based on the Project calendar working days. Can you provide an example of how project is slotting a task on a non-working day?