Is there a way to ask MS Project to verify the integrity of a project?
Especially in relation to resource allocations, I have seen several incidents, where a project starts behaving strange – not totally broken, but just flawed in one way or another. Right now, I am in a situation, where MS Project 2013 highlights all tasks in the project, when I ask it to highlight “driving predecessor tasks”……… (5 days ago, it did the highlighting correct).
I would very much like to perform integrity check, whenever saving and/or opening a project, in order to become aware of the situation as quickly as possible.