Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

Home Forums Microsoft Project Discussion Forum Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

Viewing 2 reply threads
  • Author
    Posts
    • #5079
      Avatar photoCommunity
      Keymaster

      Working offshore in the Oil & Gas industry, we incur costs based upon a minimum 12-hour day for personnel and on a minimum 24-hour day for equipment.  Is there a way to keep MS Project 2007 (or any subsequent version) from pro-rating these costs over a scheduled day of lesser duration?  Changing Default Fixed Costs Accrual under Tools, Options, Calculations doesn’t seem to have the desired effect.

    • #6706
      Avatar photoCommunity
      Keymaster

      I didn’t actually test this so I might be wrong but did you try using a 12 hour calendar?  You can also override this with a 24 hour task calendar for equipment.

    • #6748
      Avatar photoCommunity
      Keymaster

      Thanks for your reply.  The calendar used doesn’t seem to matter.  If there is a partial day the resource is still pro-rated.  This normally occurs on the first day and last day of the project, but can sometimes occur during the project as well.