Creating project inputs in hours rather than days

Home Forums Discussion Forum Creating project inputs in hours rather than days

Viewing 1 reply thread
  • Author
    Posts
    • #414162
      Liz
      Guest

      Is it possible to create inputs in hours and how would you do this in MS Project please?

    • #414163
      Jigs Gaton
      Member

      Liz, yes you can enter hours in many ways, and in many different places. Easiest? Just type Xh in the Duration column where X=hours, or do the same wherever you see the Work column. For example, using Task Details you can have a duration of 1 day, but assign resources to the task in hours (ie. me = 4h, you = 4h). Hope that helps!