Liz, yes you can enter hours in many ways, and in many different places. Easiest? Just type Xh in the Duration column where X=hours, or do the same wherever you see the Work column. For example, using Task Details you can have a duration of 1 day, but assign resources to the task in hours (ie. me = 4h, you = 4h). Hope that helps!