Custom Field code mask – change the definition

Home Forums Microsoft Project Discussion Forum Custom Field code mask – change the definition

Viewing 1 reply thread
  • Author
    Posts
    • #405190

      I have a custom field in PWA that was set with a code mask of “*.*”. Now the field cannot be used in a filter.
      Is there a way to change this to a “*” only so that is can be filtered?

    • #405211
      Avatar photoLarry Christofaro
      Participant

      Norman, good question. I actually tried it and was unable to change the code mask. To the best of my knowledge, you’ll need to create a new field and copy the old values to the new. I hope someone has a better idea…